MSP Retained logic or progress overide

Frank NealMember for 23 years 8 months
Created
3
3
0
Does anyone know if MSP uses Progress overide or retained logic or something else.?

3 replies

Oldest first
  1. 0
    Frank Neal ·
    I have just run a test myself and it appears to be Retained Logic...unless someone else knows better!
    Are there any adjustable settings in MSP?
  2. 0
    Paul Harris ·
    Not quite as simple as that, this is MSP.

    Retained logic when:
    1. Splitting Inprogress tasks is checked in Options and
    2. The percentage complete is greater than 0% when there is an actual start.

    Otherwise Progress override.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  3. 0
    Abdullah Merchant ·

    Hey Paul,   I just picked up

    Hey Paul,

     

    I just picked up your book.....99 tips and tricks with MS Project 2007. Thanks a lot for helping people like me in getting a jump start with MS Projet scheduling.

    I am about to start planning a Project involving working on Gas piping and Utility area rebuilding. My project manager want us to maintain a Risk register, to be reffered to and discussed during our review meetings . I was wondering if you could guide me as to where i could find more information on this. I am familiar with the P6 Risk Register.....but i am relativeley new to MS Project.Is there any excell sheet available that may can be used efficiently, or any options available with MS Project 2007. Thanks again.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?