Changing Date ..Man Hours Change

zulfi AliMember for 21 years 11 months
Created
2
2
0
Hi Friends, I

I have a problem and need your help to fix it ut. I work on P3 but, had to work on MSP.
Whenever I change activity duration and date , activity resource manhours also change, could you please help to fix it up.

Thanks

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Ali,
    Double-clic the task to open "Task Information", display "Advanced", change "Task Type" to "Fixed Work" to have the assignement rate changed instead of the amount of work.
    Select together all the tasks you want and click the Task Information icon, then continue as above
    Open Tools, Options, Schedule and change Task Type to Fixed Work to setup the tasks before you create it.
    All the best
  2. 0
    zulfi Ali ·
    Thank you very much Alexandre. Only one activity still showing the same attribute. Let’s see
    Once more thanks a lot for your kind information.