Progress line question (Bug?)
In the Open Standard
Ewald LangezaalMember for 21 years 4 months
- Created
- 3
- 3
0
When my project is in hours(and so is my graphic timescale), current date and status date can also be showed at every hour of a day, but I can not set the progress line in hours
the progress line will allways start between the end and beginning of two days
is this a MSP weakness?
sSecond, when a task is planned ahead of the progress line (status date)has progress MSP’s progressline shows a progress hook to the right, and that is ok, but it also showes a progress hook to the successor of this task which has not been started at all, instead of this the progress line should stay on it’s status date (no hook to the right but a vertical line) is this a bug or is there a setting that deals with this?
the progress line will allways start between the end and beginning of two days
is this a MSP weakness?
sSecond, when a task is planned ahead of the progress line (status date)has progress MSP’s progressline shows a progress hook to the right, and that is ok, but it also showes a progress hook to the successor of this task which has not been started at all, instead of this the progress line should stay on it’s status date (no hook to the right but a vertical line) is this a bug or is there a setting that deals with this?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?