External task ?

Andrew OwensonMember for 20 years 11 months
Created
3
2
0
hi Guys

I am trying to connect two projects. I looked up the subject in help and did what it told me - however MSP said that it could not find the file. What am I doing wrong?


Many Regards

Andrew

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Andrew,
    1. open all the individual project files you want to conenct
    2. window, new window, select the open projects
    3. create the appropriate task relations, using the mouse
    4. save the files (the FILES)
    5. DO NOT move the files from the Windows explorer
    All the best
  2. 0
    Andrew Owenson ·
    Alexandre

    Genius! Why doesn’t the help section speak in english!.

    Many thanks


    Andrew

  3. 0
    Alexandre Faulx-Briole ·
    Andrew,
    you should ask MS why; they certainly have people able to write in plain English
    if you are using MS Project 2003, have the Guide a try, very good
    Alexandre