Hello,

I am working in several projects, using MSP 2007. The total amount of project that is in motion is approximately 10 at the time.

I have made me a master file in MSP that will monitor my projects, but the master file do not update it self. I need to open the last project file and the master file to be able to update the master file.

I want the master file to update it self without opening the actual project file all the time. Is this possible?

Hope you understand my problem

Regards

Dan

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Dan,

    Maybe you can keep the file open and try to search for an auto save every few hours.

    With kind regards,

    Samer
  2. 0
    Dan Mårtensson ·
    Hi Samer,

    I think your way is working, but it would be nice to have this autmated.

    Thanks

    Dan
  3. 0
    Samer Zawaydeh ·
    Dear Dan,

    I am glad that it worked. I will keep it in mind to solve in the future, if someone else does not come with an answer.

    With kind regards,

    Samer