Custom Resource Curves

Hemanth KumarMember for 23 years 11 months
Created
2
3
0
Can we make custom resource curves in MSP

none of the default Curves(Bell,Turtle Etc) match My Resource

2 replies

Oldest first
  1. 0
    James Griffiths ·
    Hi Hemanth,

    Yes you can input a custom resource curve against every individual resource on every individual task. All you need do is go into the Task Usage or Resource Usage View. Make sure that the right-hand side of the screen is showing WORK, then input the daily hours that you expect the resource to work. Of course, you must have allocated a resource to the task in the first place

    I will say, though, that the whole exercise is nearly a complete waste of time. As soon as you input ACTUALS, the system will automatically re-schedule the profile according to the Task Type(Fixed Work, Fixed Duration or Fixed Units) and the amount of work previously done.

    James.
  2. 0
    Hemanth Kumar ·
    thank you mr james

    but i want to create a resorce profile template ( As I Do In P3)
    and use it for my activity

    i will be entering for an activity : duration,resource profile and budjeted qty, i dont know on what day how much resource, but want to know that.....


    thanks