Project Base Calendar

Julian CoetzeeMember for 20 years 4 months
Created
2
2
0
Hello Guys

I have asked this before and was wondering if the new MS Project software (2007) has a remedy for my problem.

The problem is task calendars clashing with the Project calendar that you set up in the Tools Options window. If I have a standard calendar setting in the Tools Options Window and want to set a task to a 24 hour calendar, the task duration goes haywire and causes confusion.

It is driving me mad.

Thank you

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Julian

    2007 will not solve your problem, nor will any Primavera product.

    The only way I have found to resolve the duration calculation problem is to use say the Number1 field and create formula to calculate he correct value in this field.

    For example the formula below will give the correct duration for a 24 hour calendar when the Tools, Options, Calendar, Hours per Day option is set to 8.

    IIf([Task Calendar]="24 Hours per Day",[Duration]*0.33,[Duration])

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Julian Coetzee ·
    Thank you very much for that tip!

    Keep Well!