Security in MSP

Andrew OwensonMember for 20 years 11 months
Created
2
2
0
Everyone

I am trying to share one of my projects on a web portal. Is there anything stopping people changing or copying the plan either by mistake or intention. I have a read-only on the plan, but people can save and re-name, pdfs are ok, but I want people to update the plan to indicate progress.I also have a choice of views which I want people to use, and so I would like the options to be flexible. I am using 2003

Many regards

Andrew

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello Andrew,
    the only possible way is by using MS Project Server; the people involved in your project would enter their actuals in Project Web Access (the Web interface of MS P Server) timesheets.
    you cannot protect the project baseline on one hand and let the current unprotected.
    Cheers
    Alexandre
  2. 0
    Andrew Owenson ·
    Alexandre

    I thought as much, but wanted to make sure. Thanks

    Andrew