How reliable is peak unit values.?

Vinod RaturiMember for 20 years 2 months
Created
1
4
0
Hi All,

I was trying to experiment on smaller scale for resource assignments. The steps involved were ,

1) I created a task with different combination of characteristics like fixed duration ( effort driven ) , Fixed duration ( with effort duration off ) , fixed units ( effort driven and effort driven off ) & fixed work.

2) Duration of 44 hrs were assigned to tasks.

3) resouce assigned was 1 unit for each task.

4) in task usage view , last day 4 hours was changed to 16 hours , since on that day two person ( i hoped ) will work.

5) In final stage , i saw for all the tasks , peak resource assignment in graph on last day was showing 6 , contrary to what i expected that max it should be 2 , since two resources would be sufficient to complete 16 hours of work on last day.

IS this behaviour normal ?

Thanks,

with regards,

vinod

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Vinod,
    as you entered 16 hours on the last day, MS Project put the all 16 hours at the same time where the initial 4 hours were, the morning.
    click zoom in (the magnifier +) to see the time more in details
    if you want to spread the 16 hours during the whole day, enter 8 hours during the morning and 8 hours in the afternoon; ms project will display a warning saying the resource is assigned beyond the task limit on the fixed duration tasks; click OK
    the resource graph will show peak unit = 2.
    Alexandre