Skip to content

MS Project 2002 vs MS Project 2003

Rodel MarasiganMember for 19 years 11 months
Created
6
3
0
Is any body aware of this issue? A project done in MS Project 2003 and open on MS Project 2002 has a different result end-date after re-scheduling? I try to resolve the issue by changing calendar or working time but it seems no effect. I open it again in MS Project 2003 and re-schedule and give me back to original end-date again. I also convert it to P3e and give me different end-date again. The problem is the client using MS Project 2002 and having different end-date on my submission. If anybody aware of this and know the causes kindly advise and it’s very much appreciated. Thank you very much in advance RCM PCMgr UGL QLD, AUST

6 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Rodel,

    Do the best you can to acquire same version of MS project as the client.

    Otherwise, you have to live with the same problem that repeat and repeat until completion of your project.

    This is because it is very clear in MS Project 2003 that the new version is totally different from previous versions.

    Cheers

    Charlie
  2. 0
    Alexandre Faulx-Briole ·
    Rodel and Charleston-JOseph,
    strange behavior, because MSP 2003 was supposed to be only a restyling of MSP 2002
    I do have this kind of result (or mistake) with MSP in French, because as of the 2002 release the basic standard calendar the working day is only 7 hour long
    Could you send your file to afaulxbriole@wanadoo.fr?
    Regards
  3. 0
    Charleston-Joseph Orbe ·
    Hi Alex,

    At present, I don’t have files in MSP2003. A colleague of mine from previous collaboration loaded MSP2003 in my laptop and we used to prepare our proposal in MSP and P3, but the final submission was in P3.

    So my laptop got corrupted and was re-formatted. There was no partition so all files gone.

    I come to know about this differences because I read books MSP2003.

    so i cannot sent you any files.

    regards,

    Charlie
  4. 0
    Rodel Marasigan ·
    After a thorough review on programme and logic comparing MSP2002 and MSP2003 I arrive on a conclusion that the main cause of the different output is because of the relationship calendar lag duration used are different from each other. MSP2002 uses the predecessor’s calendar on lag while MSP2003 use the successor’s calendar.

    P3e/ PM5 have an option to select which calendar to be used on lag before re-scheduling.

    Regards,
    Rodel
  5. 0
    Paul Harris ·
    I have just run some tests with 2007, 2003, 2002 and 2000 versions.

    I have found that by adding 2 tasks of 1 day duration and setting the second task to a 24 hour calendar and connecting the two tasks with a FS +5D that 2007, 2003, 2002 calculate on the successor calendar and 2000 on the project calendar as set in the project overview form.

    Rodel, give me a call sometime to discuss, 04 1118 7701.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  6. 0
    Rodel Marasigan ·
    Hi Paul,

    I do same exercise of what you did on MSP2002 & MSP2003 and gave me different result as shown below.

    MSP 2003 result
    Task Name     Duration     Start          Finish          Predecessor      (Calendar)
    Sample      3d     Tue 27/02/07     Thu 1/03/07     
    Act1          1d     Tue 27/02/07     Tue 27/02/07                    Standard
    Act 2          1d     Thu 1/03/07     Thu 1/03/07          2FS+5d          24hr

    MSP 2002 result
    Task Name     Duration     Start          Finish          Predecessor (Calendar)
    Sample      6d     Tue 27/02/07     Tue 7/03/07     
    Act 1          1d     Tue 27/02/07     Mon 27/02/07                    Standard
    Act 2          1d     Mon 6/03/07     Tue 7/03/07          2FS+5d          24hr

    It clearly shows that MSP2003 used successors calendar on relationship lag while MSP2002 used predecessor’s calendar.

    I try to contact you but unfortunately I did not manage to get through.

    Regards,

    Rodel

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?