Skip to content

MS Project 2003 - Vertical milestone line

John MatthewsMember for 19 years 7 months
Created
2
6
0
Other than using the drawing tool to physically put a vertical line through a Gantt chart, is there any other method of putting a vertical line through the chart.

I would ideally like to highlight a couple of key project phase milestones by having a vertical line through the Gantt chart view (similar to the ’current date line’). Drawing a line is okay but I would prefer if it I could anchor it to a milestone in some way but cannot see a way of doing this.

2 replies

Oldest first
  1. 0
    James Griffiths ·
    Hi John,

    You should be able to "anchor" your line to a milestone. When you have drawn the line, double-click on it. Click on Size& Position. It’ll give you the options (this is what it does in MSP 2000)

    HTH.

    James
  2. 0
    John Matthews ·
    That worked fine in MS2003 also. Thanks for the advice.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?