weightages to actvities
In the Open Standard
Bhadri VakacherlaMember for 19 years 8 months
- Created
- 7
- 4
0
I have three queries...
1) Is it possible to assign weightages to activities while calculating the overall progress of the project? If so plz tell me the option available...
2) Is it possible to draw a ’s’ curve in Ms-Project itself?
3) How should we prepare the target ’s’ curve?
Even though i have billing breakup...i cannot take it....because...money spent is not exactly matching with the actual work progress....my pre assigned weightages are not matching upto mico-level works...for instance...i know the total quantities of earthwork,PCC and RCC...but i have the weightage for foundation activity as a whole...and more over some structures hav different times for all of these...
1) Is it possible to assign weightages to activities while calculating the overall progress of the project? If so plz tell me the option available...
2) Is it possible to draw a ’s’ curve in Ms-Project itself?
3) How should we prepare the target ’s’ curve?
Even though i have billing breakup...i cannot take it....because...money spent is not exactly matching with the actual work progress....my pre assigned weightages are not matching upto mico-level works...for instance...i know the total quantities of earthwork,PCC and RCC...but i have the weightage for foundation activity as a whole...and more over some structures hav different times for all of these...
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?