Progress recording methods
In the Open Standard
Iftikhar Awan P.Eng.Member for 20 years 4 months
- Created
- 5
- 2
0
Hello.
Is it true that in MSP, the remaining duration and % complete of a task are always linked, and there is no other option to record task progress?
In P3, P5 and Suretrak, we do have the options of unlinking the two or to link % complete with resources when they have been assigned to activities. Does the latest version of MSP offer these options?
Is it true that in MSP, the remaining duration and % complete of a task are always linked, and there is no other option to record task progress?
In P3, P5 and Suretrak, we do have the options of unlinking the two or to link % complete with resources when they have been assigned to activities. Does the latest version of MSP offer these options?
5 replies
Oldest firstLog in or join to reply