Progress lines

Bhadri VakacherlaMember for 19 years 8 months
Created
1
2
0
After updating tasks as per the status date, i have updated the project "as though work scheduled from that date"..and the schedule gave me a new tentative date of completion...but in the next month if i want to add new information...is it correct if i simply update each of the tasks...i think its not correct...should i remove my earlier update and start updating frm the beginnning...?
Isnt it laborious when we hav a thousand activities...?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Bhadri,

    I don’t see any advantage of removing and updating all the activities/ task which was previously updated. The important here is the logic behind wether it change or maintain due to additional information. The only difference it may occurs is the original baseline against your new added information which is not carry over after adding new information. It means that the new information is not reflected on your original baseline.

    Hope this help

    Regards,
    Rodel