Merging MSP Plans

Mark ChapmanMember for 20 years 5 months
Created
14
5
0
I have 2 plans in MSP but now want to merge them. Now they use different calendars;

1. A normal 5 day week calendar
2. 24 hour calendar

What do I need to do my plans so I can copy and paste one into another? Or is there a better way to merge them.

Cheers in advance.

14 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Mark and Quiamco,
    Better use "Insert, Project" than Copy and Paste to merge one project into another, you won’t lose any data that way; be carefull to summarize the target project at the minimum and place the cursor where you want the inserted project to take place, to avoid the inserted project to become a subsidiray task in the target project.
    Alexandre
  2. 0
    Mark Chapman ·
    Thanks Alexandre & Quiamco,

    When I copy the 5 day plan into the 24 hour plan, it decreases my durations by a third. Which isnt a surprise but I am not sure the best way forward. The fact that its a duration and not effort is the problem. I want to keep my 5 day duration as a week’s work. So in the 24 hour plan this will convert to 98 hours or 7 days and not 1.67! I would need to multiply by 21/5 but I am not sure where or how to do this.

    Alexandre, I see when I insert the project it continues to link to the original file but I don’t this. I will try unclicking the "link to project" to resolve this.
  3. 0
    Mark Chapman ·
    deliberate mistake - 168 hours per week!
  4. 0
    Alexandre Faulx-Briole ·
    Mark,
    MS Project only has ONE setup for how many hours in one day; that’s why you have this problem.
    Paul Harris has designed a formula to get correct task duration whenever the task calendar is not the regular one, you will find it at
    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=4&Top=28177
    Hope it helps,
    Alexandre
  5. 0
    Mark Chapman ·
    Hi Alexandre,

    I am making slow progress. I am importing my 5 day week plan into the 24 hour shutdown plan. I think I maybe best to remove actuals first and then insert this project.

    These activities are using the default calendar, "none" and I have modified Paul Harris’s formula to this:

    =IIf([Task Calendar]="None",[Duration]*21/5,[Duration])

    However I am not sure how to set this calculation into a number field first and then the duration field.

    Also what is the "I" before the "IF"?
  6. 0
    Alexandre Faulx-Briole ·
    Mark,
    You’re right, it’s best to insert a project with no actuals; Iif means "Immediate If", it is the same as the regular "If, Then, Else" in a spreadsheet app;
    go to Tools, Customize, Fields, then select a duration field and create the formula in there; then in the gantt chart spreadshhet columns, replace the usual Duration field with the field that contains the formula.
    Alexandre
  7. 0
    Mark Chapman ·
    Thanks Alexandre for your help. It’s worth keep the notes here so everyone else can use as reference.

    The help above was excellent but this had led to more questions:

    1. I see my formula has some inconsistancies, ie anything that’s not a week long. So rounding down will work for the majority of the time but will "rnd" work? Or is there a formula for "remainder" then I could work out exact figure.

    2. The duration is calculated in days which is fine for the imported plan but I don’t want the shutdwon plan converted to days too. I can change the duration unit to either hours or days but I want to leave those in days as days and those in hours as hours.

    3. In the old 5 day week plam the activities started at 8am and finished at 5pm but in the new plan the activties start and finsh at 00:00 despite 23:59 being set in options/calendar???

    Look:

    24 Hours 8 days 03 Apr 00:00 11 Apr 00:00
    24 Hours 0 days 11 Apr 00:00 11 Apr 00:00
    24 Hours 28 days 11 Apr 00:00 09 May 00:01
    24 Hours 7 days 09 May 00:01 16 May 00:01

    4. Why 00:01???

    Thanks,

    Mark




  8. 0
    Anoon Iimos ·
    that means there’s a lag of one (1) minute FS - with one minute lag
  9. 0
    Mark Chapman ·
    No constraints on any of these activities!

    I have been tinkering further and this now happens:

    24 Hours 7 days 03 Apr 00:00 10 Apr 00:07
    24 Hours 28 days 03 Apr 00:00 01 May 00:28
    24 Hours 7 days 03 Apr 00:00 10 Apr 00:07
    24 Hours 28 days 03 Apr 00:00 01 May 00:28

    So whatever my duration, say x, then there will be x minutes!
  10. 0
    Mark Chapman ·
    OK I sorted this out as I am used to P3 and I had put the finish time as 23:59 and initially (1st problem) I had changing the working time just for 1 day.
  11. 0
    Alexandre Faulx-Briole ·
    Mark,
    in MPS make sure your 24 hour/day calendar is open 00:00 to 00:00; it’s not the same as P3!
    I don’t know why you have these strange finish date/time; can you pls send an example of this to afaulxbriole@wanadoo.fr
    Thanks,
    Alexandre
  12. 0
    Mark Chapman ·
    Hi Alexandre,

    I just created a one line activity with a 28 day duration using a 24 hour calendar. You then need to change working time to 00:00-23:59. The EF date will be 00:28. Is this what you wanted? Or did you want something else?

    In the end I merged plans using the formula but manually rounding down when there was a percentage.

    However, I see me having this problem regularly. So would like to know how to convert a duration into an integer and back again as some of the functions like round can only be used on integers.

    Cheers,

    mark
  13. 0
    Alexandre Faulx-Briole ·
    Mark,
    change working time to 00:00 - 00:00! 23:59 is Primavera P3, NOT MS Project; in MS Project, that makes every single day 1 minute shorter, and to work 24 hours you v will need ONE day PLUS One minute
    Alexandre
  14. 0
    Mark Chapman ·
    I totally agree and I had worked this out 2 days ago. C’est le vie!

Log in or join to reply