ms project

Ahmed EwisMember for 19 years 8 months
Created
3
3
0
i have a project which is charactrized by that
all tasks are fixed units
now i have the gant chart i have all resource assigned
but i want now to enter for each activity the precentage of the work done
and to show this precentage on the gant chart
well i know how to show this by going to bar style and from text ill choose
% complete
but i saw 2 things there
% Complete and
% Work Complete
what are the difference
between them and how can
i enter the % of the work done

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Ahmed,

    % complete is duration and % work complete is resources or hrs. There are many ways of entering progress. You can double click the activity and enter percent complete from general tab of task information dialog box or by inserting column to show % work complete and % complete. Another way is to display the custom form icon from toolbars. View-> Toolbars-> Custom Form. Then select the form Work tracking.

    HTH,
    Rodel
  2. 0
    Ahmed Ewis ·
    thanks for trying to help me but my tasks in the project are fixed units tasks when i did what u said i found out that % complete and % work complete are the same value while its a project for installing pipes and cables and some other stuff like air conditioing units
    so i really can get it and im the consultant which is playing a part with the project owner and i have to follow the contractor if he is behinde the schedual or not??
  3. 0
    James Griffiths ·
    Ahmed,

    You can enter the ACTUAL WORK (hours) by changing the VIEW to TASK USAGE. On the right-hand side of the screen, you will see the cells that enable you to input the actual hours completed, on whatever days you choose. This will then automatically calculate the % Work Complete (hours). If you then change the remaining task duration, this will automatically change the % Complete (duration). However, you must be careful, because when you change the remaining duration, you are also likely to automatically change the Remaining Work (hours) - thus altering the % Work Complete.

    There is no One-Button solution. If it is a Fixed Unit task, then changing the duration will automatically change the hours. If you don’t want this to happen, then you must change the task-type to that of Fixed Work.

    James.

Log in or join to reply