Default Startup Date
In the Open Standard
Mudar BahriMember for 19 years 5 months
- Created
- 4
- 3
0
I had a project plan that started at March 1st. I save the same plan to be used for another project that will start on May 20th. The two projects are very similar.
The problem is that everytime I start the new plan in MS Project the view of the gantt chart starts at March 1st not May 20th.
The earliest task will start at 20 May and the project information tell that project start date is May 20. Why the view insists on starting at 1 March??
Please help
TIA
The problem is that everytime I start the new plan in MS Project the view of the gantt chart starts at March 1st not May 20th.
The earliest task will start at 20 May and the project information tell that project start date is May 20. Why the view insists on starting at 1 March??
Please help
TIA
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?