how can i do it

Ahmed EwisMember for 19 years 8 months
Created
1
4
0
how can i show on Gantt chart on the task bar on the right side the % work done and on the left side the % of remaining work but to be percent not hours or days

1 reply

Oldest first
  1. 0
    Trevor Rabey ·
    Easy.
    First, it is better to create a new VIEW for this, rather than changing one of the built-in VIEWs.

    % Work Remaining = 100 - % Work Complete

    Use a spare Number field/column, such as Number1, to do the calculation (Tools, Customise, Fields).

    Number1 = 100-[% Work Complete]

    Then use a formula in a spare Text field/column (Text1, Text2) to include the "%" sign and some title text for the display:

    Text1 = [% Work Complete] & " % WORK COMPLETE"
    Text2 = [Number1] & " % WORK REMAINING"

    For convenience, rename Text1 and Text2

    Text1: PERCENT WORK COMPLETE
    Text2: PERCENT WORK REMAINING

    Then use Format, Bar Styles, Text (tab) to show Text1 and Text2 on the ends of the bars.