how can i do this

Ahmed EwisMember for 19 years 8 months
Created
3
4
0
well i have a ms project file and i have some delayed activities and i wanna show my boss each activity delay in days compared to the intial plan
how can i do it nowwwwwwwwwwwwwwwwww plzzzz??

3 replies

Oldest first
  1. 0
    Ahmed Ewis ·
    yes i did but i want an empty cell telling me that this activity is delayed by 20 days or 10 and so on for each activity can i add an empty column and make formula to substract the start date of every activity and the status date???
  2. 0
    A D ·
    Hi Ahmed,

    There must be a column of DURATION VARIANCE. Double Click on the column head and add this column in the field name.

    This shud solve ur problem
  3. 0
    Dave Hamblett ·
    you can use start or finish varience columns to show this or if you are using 2003 or later there is a wizard to compare 2 project files and listt all the changes between them

    hope that helps

    Dave