schedule tasks by date and time
In the Open Standard
Mike SohaMember for 19 years 1 month
- Created
- 1
- 3
0
i’m new to project; just a couple days into it actually - what i’m trying to do is schedule a reoccuring task specific to date and time. by date is easy enough, but i want it to start at 9:30 am and end at 10:00 am.
i also notice that task itself will show the duration in outline level 1 as 8hrs long when the duration in outline level 2 shows the duration as .5hrs; why is it doing this?
thanks for any thoughts/relies
i also notice that task itself will show the duration in outline level 1 as 8hrs long when the duration in outline level 2 shows the duration as .5hrs; why is it doing this?
thanks for any thoughts/relies