S - Curve

Sivalingam PrabagaranMember for 19 years 1 month
Created
5
4
0
currently i’m checking a work programme for a highway
construction. my question is ... is it possible to
produce S-Curve based on cost of the project by tracking
the programme on the last day of every months ..

thanks ..

PS

5 replies

Oldest first
  1. 0
    J Venkatesh PMP PSP ACIArb ·
    yes...u can....

    plot a S-Curve in excel based on the monthlwise cost which can be extracted from MSP - Reports...This will be ur plan and track the same against the actual bill/Invoice amount done every month

    J
  2. 0
    Md Dasuki Samad ·
    Can explain it further? I’m facing a difficulties and confused on how to plot the physical as well as financial curve...
    Please give info.

    Thanks.
  3. 0
    Trevor Rabey ·
    I see no one has replied to your question for a week or more, so here is an answer.

    What do you mean by "physical" S curve? What is it exactly that you are wanting to plot?

    If you want to draw a graph you just need two axes and some data.
    The common S curves are Cumulative Cost and Cumulative Work (hours) with time on the independent, horizontal axis.
    You could plot cumulative m3 of concrete or cumulative bricks or cumulative metres of pipe in the trench, against time. But if whatever you are trying to graph doesn’t have any data associated with it then you are all out of luck.
  4. 0
    Md Dasuki Samad ·
    Thank you for replying me. Actually i already read and try some of the suggestion in the related topic on this discussion boards, and it’s really works.
    A very much thanks to you again.
  5. 0
    J Venkatesh PMP PSP ACIArb ·
    Dasuki,

    incase, if u need any further help, mail me at venkat79_j@yahoo.co.in

    Jaya