Hi All,

I need to be able to get the contents of the notes box in MS Project exported to Excel. The problem I am getting is that when I use bulleted points in the notes box, only the first bullet point is exported.

Is this a known bug or a software constraint that cannot be fixed? I am running MS Project 2003 with the KB832887 patch.

Cheers

Jimbo

1 reply

Oldest first
  1. 0
    Niek Zonneveld ·
    Yep this is a known issue.

    The notes field contains data in HTML format which is garbled if you export to Excel.

    H.T.H.

    Niek.