MS Project Server - New Forecast Dates
In the Open Standard
Scott AnthonyMember for 18 years 10 months
- Created
- 1
- 5
0
In Project Web Access, when a resource is assigned to a task, he is only allowed to enter the % complete and /or the remaining hours. He cannot change the start/finish fields. I am trying to devise a good way to facilitate the resource in communicating a change to these dates to the project manager. None of the options I have thought of seem to be very efficent:
1) attach an issue to each task noting the date changes
2) attach a document to each task like a spreadsheet that shows the is/was for each date change
These both seem undesirable because a resource is dealing with with hundreds of tasks each day that may have date changes.
I need help in figuring out a way for a resource to communicate forcate date changes efficiently within Project Web Access.
Thanks!
1) attach an issue to each task noting the date changes
2) attach a document to each task like a spreadsheet that shows the is/was for each date change
These both seem undesirable because a resource is dealing with with hundreds of tasks each day that may have date changes.
I need help in figuring out a way for a resource to communicate forcate date changes efficiently within Project Web Access.
Thanks!
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?