P4 vs P5

Lyle MarsdenMember for 19 years
Created
3
2
0
Hi,

Could anyone advise what benefits P5 has over P4?

I am currently using P4. My company is converting to P6 in 6 months (but the process is slow as my company has over 1500 users worldwide)

My boss has asked me to investigate if its worth converting to P5 for the next 6 months - until P6 is up and running.

Would appreciate any useful feedback

3 replies

Oldest first
  1. 0
    Dragan Ilic ·
    Lyle,

    take P6 and get training. Forget about P4 and P5 they are now the history.

    Every 2 years take new program from Primavera. And training.
    Maintenance is 2 years.

    If you provide this system you can get your planners, hardware and software operational for every project.

    Otherwise you will face HR department which is more difficult then IT.

    Good luck!

    ilic@eim.ae
  2. 0
    Lyle Marsden ·
    Dragon,

    Thanks - sounds like good advise.
  3. 0
    Paul Harris ·

    There were a significant number of enhancements in the P5 Client Server version including:

    Undo
    WBS Summary Activity
    EPS Level Activity Codes
    Activity Step Templates
    Assignment Staffing
    Resource Security
    Improved Baseline Functionality
    Progress Spotlight
    Suspend and Resume
    Store Period Performance
    Advanced Scheduling Options
    Rates for Roles
    Excel Import and Export Tool
    P3 Subproject Import
    Export to Primavera Contractor Version 4.1
    Audit Trail Columns
    Enhanced or New Graphics Functions
    Bar Label Placement
    Three Timescale Units
    Vertical Sight Lines
    Reorganize Automatically
    Gantt Chart Curtains
    Improved Report Wizard Functionality

    It is worth going from P4 to P5 Client Server, but you don’t need to rush to P6 if you are using the Client Server version as there are not many improvements here. Most of the improvements were in the web interface.

    P6 Client Server Enhancements were:

    XML File Format for Import and Export
    Copy an Existing Project with Baseline
    Role Limits
    Reflection Projects
    Manually Edit the Resource Usage Spreadsheet
    Owner Activity Attribute used with Reflection Projects
    Resource Assignment Audit Trail
    Project Layouts
    Group and Sort Enhancements
    View Planning Resources assigned with the web interface
    Curtains and Spotlights Enhancements

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply