Combining schedules

Ladi SodipoMember for 18 years 11 months
Created
3
4
0
I have to combine a fully resourced schedule with another schedule that is not resource loaded, what is the best way to combine this schedules effectively without affecting dates on my resource loaded schedule.

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    if you do not want to assign resources to your second schedule: open both files, click Window, New, select both files, click OK
    if you want to assign resources to your second schedule: open both files, select te second file, click Tools, Shere Resources, Share resources, click Using resources of, select the 1st file in the list, click OK
    That’s it
    Alexandre
  2. 0
    A D ·
    Hi alex,

    Wil u plz elaborate on ur first line. If u click window, then there is no option of NEW.

    Also, there is no SHARE RESOURCE option in tools menu.

    Which version of Primavera u r using. This is P5 or P6.

    Plz explain

    Ravi
  3. 0
    A D ·
    Sorry Alex,

    My apologises,

    i thought I was in P3 thread.

    Extremely sorry. I got it what u wanna say.

    Cheers,

    Ravi