MS Project won’t save baseline
In the Open Standard
Bo JohnsenMember for 20 years 7 months
- Created
- 0
- 4
0
For one single programme I have a problem that MS Project (2000) won’t save the baseline values. I can manually copy the rows from start/finish/duration into baseline start/finish/durations so no overall problem, but it won’t update automatically when I try to do a "Save Baseline - Entie Project".
There is no problem clearing the entire baseline and I have no problems saving the baseline in other programmes, just this one.
Have tried to save to MPD format and then back to MPP and also tried to make a new file with same base calendar, imported the problem file with "Link to Project" unchecked, outdented all activities one level, deleted ID#1, thereby getting a copy of old file with same data, but again without luck.
Any ideas where the problem could be?
Best regards,
Bo
There is no problem clearing the entire baseline and I have no problems saving the baseline in other programmes, just this one.
Have tried to save to MPD format and then back to MPP and also tried to make a new file with same base calendar, imported the problem file with "Link to Project" unchecked, outdented all activities one level, deleted ID#1, thereby getting a copy of old file with same data, but again without luck.
Any ideas where the problem could be?
Best regards,
Bo
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?