Resource Loading In MS Project
In the Open Standard
Adekunle ArisilejoyeMember for 18 years 6 months
- Created
- 3
- 3
0
Hi,
Please, how do I add multiple resources to a fixed work task type, with the resoures having the same units.
e.g Piping Engineer = 14hrs
Mechanical Eng. = 16hrs,
total work is 30hrs(I want it fixed). Naturally MP assigns a days of work for the task. But I want it done in 5days with the 2resource persons working tru d 5days. I tried doing it but MP cntrols the unit percentage, hence my histogram was wrongly affected.
Any ideas.
Cheers,
Kunle
Please, how do I add multiple resources to a fixed work task type, with the resoures having the same units.
e.g Piping Engineer = 14hrs
Mechanical Eng. = 16hrs,
total work is 30hrs(I want it fixed). Naturally MP assigns a days of work for the task. But I want it done in 5days with the 2resource persons working tru d 5days. I tried doing it but MP cntrols the unit percentage, hence my histogram was wrongly affected.
Any ideas.
Cheers,
Kunle
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?