Resource Loading In MS Project

Adekunle ArisilejoyeMember for 18 years 6 months
Created
3
3
0
Hi,

Please, how do I add multiple resources to a fixed work task type, with the resoures having the same units.

e.g Piping Engineer = 14hrs
Mechanical Eng. = 16hrs,
total work is 30hrs(I want it fixed). Naturally MP assigns a days of work for the task. But I want it done in 5days with the 2resource persons working tru d 5days. I tried doing it but MP cntrols the unit percentage, hence my histogram was wrongly affected.

Any ideas.

Cheers,
Kunle

3 replies

Oldest first
  1. 0
    Trevor Rabey ·
    Set the Task Duration to 5 Days.
    Assign the 2 Resources at 100%.
    Set the Task Type to Fixed Duration, effort driven on.
    Switch to the Task Usage View.
    Type in 14 hours Work for the Piping Engineer.
    Type in 16 hours Work for the Mechanical Engineer.
    The Duration will not change while you make the changes.
    MSP will spread the hours for each Resource over the 5 Days, 2.8 hours/Day and 3.6 Hours/Day respectively.
  2. 0
    Adekunle Arisilejoye ·
    thanks man will try it out asap.

    cheers
  3. 0
    Adekunle Arisilejoye ·
    bingo,

    Worked man, thanks alot. But why didnt it work. I set it to fixed duration but just cos I didnt put 100%units it didnt.

    Cheers man

Log in or join to reply