Creating Targets in Project

Jon WardMember for 18 years 4 months
Created
4
4
0
hello all,
any help would be very much appreciated,, i am currently quite proficient with Primavera Version 3,, i have very recenetly moved over to MS Project,, could any one give me a very quick heads up on how to create Targets, or what Project calls Targets so i can use the Help Function in MS Project.
many thanks

4 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Jon,

    Welcome to the dark side. :o)

    I use MS Project but haven’t used Primavera, so if you could expand a little on what you mean by targets, then I may (or may not) be able to help.

    Regards,

    Darren
  2. 0
    Jon Ward ·
    the dark side lol,,
    in P3 you can basically create an entire copy of your project i.e baseline the schedule the display the activity bars for every activity below the ’live’ activity bars,, that way you can see easily what has slipped and what is ahead of schedule,, you can also show Planned Percentage (of the baseline) against the actual percentage
    many thanks
  3. 0
    Darren Kosa ·
    Jon,

    OK, I’m with you now. Setting the baseline is straightforward enough Tools > Tracking > Save Baseline. Check the ‘Save Baseline’ and ‘Entire Project’ radio buttons and click OK.

    Displaying Planned % Complete is a little more difficult and requires some customisation.

    Check out the thread below that Niek Zonneveld started, it should give you the solution you need.

    Display Baseline Percent Complete In MS Project

    Regards,

    Darren
  4. 0
    Jon Ward ·
    thanks Darren,
    very very much appreciated
    best regards
    jon