(F9) re-schedule in MS Project
In the Open Standard
Jon WardMember for 18 years 4 months
- Created
- 3
- 4
0
hello all,
i am used ot working in P3, could anyone tell me the correct way to re-schedule e.g F9 in P3
many thanks
also,,
again, in P3 i can make all of my activities ’fall’ in sequence, eg. listed in decending order, so if activity 1 comes after activity 2 then activity 2 would be top of the listing
many thanks
i am used ot working in P3, could anyone tell me the correct way to re-schedule e.g F9 in P3
many thanks
also,,
again, in P3 i can make all of my activities ’fall’ in sequence, eg. listed in decending order, so if activity 1 comes after activity 2 then activity 2 would be top of the listing
many thanks
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?