DEAR ALL,
1. HOW TO SCHEDULE A MS PROJECT SCHEDULE ( AS IN P3 WITH A DATA DATE)
2. HOW TO ADD A TARGET ( BASELINE ) TO A MSP SCHEDULE?

REGARDS
DEB

6 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Deb,

    By Data Date I’m assuming you mean Status Date (the last date the project was updated).

    Project > Project Information

    You can also set the Project Start / Finish Dates and Current Date this way.

    To set the project baseline.

    Tools > Tracking > Save Baseline

    Regards,

    Darren
  2. 0
    Pranab Kumar Deb ·
    Dear Darren,
    Thanks a lot, ya by data date i mean status date only.

    Now i am having a new problem. i a changing a MSP schedule to a P3 one. in the MSP schedule there are summary activities , these are as well coming to the p3 schedule as activities with huge durations.
    Please help.
    regards
    deb
  3. 0
    Alexandre Faulx-Briole ·
    Pranab,
    P3 regards MSP summary activities as "Topic activities".
    Quote
    It is recommended that you remove all Topic Activities by promoting ALL activities to Outline Level 1 and deleting redudant Parent Activities. You will need to check that all logic is at the lowest Outline Level before promoting activities
    Unquote
    (In "Project Planning Using P3 V3.1" by Paul E. Harris)
    Alexandre
  4. 0
    Pranab Kumar Deb ·
    Hello Aexandre,
    How to do that can you please let me know in a step by step manner.
    regards
    deb
  5. 0
    Alexandre Faulx-Briole ·
    Pranab,
    it may be easier to do in P3:
    1. Define the WBS structure of your project in P3
    2. Make sure you define the upper level to represent the whole project and one level for each outline level in MS Project
    3. Apply the WBS to the activities in P3
    4. Remove all the Topic activities in P3 (run a filter saying Activty type EQ Topic to display these activities only)
    Hope this helps
    Alexandre
  6. 0
    Pranab Kumar Deb ·
    Dear Alexandre,
    Your advice is really appreciated.
    regards
    deb