dear friends

How do we track a project in MSP

3 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Faisal,

    That’s a bit of a tricky question, you can use MS Project in many ways to track progress.

    I’ll try and give you the 5 cent tour and then hopefully you can refine your question a little more.

    1) Baseline the project (effort and duration)
    2) Track actual start dates and actual effort / duration and remaining effort / duration
    3) Reschedule tasks that haven’t started
    4) Let MS Project calculate the % Complete(s)

    Regards,

    Darren
  2. 0
    Faisal Afsar ·
    i want to know three things

    1)Reschedule tasks that haven’t started
    2)Let MS Project calculate the % Complete(s)
    3) how do i know whether my project is on schedule or not
  3. 0
    Darren Kosa ·
    Faisal,

    Here’s what I would suggest...

    Reschedule tasks that haven’t started

    Tasks should be automatically rescheduled if the precedence logic is correct, if it isn’t try using lag times or reviewing the logic

    Let MS Project calculate the % Complete

    View > Table > Tracking
    By entering actual start, duration / work and remaining duration / work MS Project will calculate the % Complete(s)

    How do i know whether my project is on schedule or not

    Use the status date and progress line as an aide and check against baseline.

    Hope this helps.

    Regards,

    Darren