total float in negative for critical activities
In the Open Standard
FA
Faisal AfsarMember for 18 years 4 months
- Created
- 21
- 5
0
21 replies
Oldest first- 0TRTrevor Rabey ·Some Task or Tasks somewhere in the critical path have either date constraints which are earlier than their "natural starts and finishes, or deadlines which are earlier than their finishes, or both, and so all of their predecessors therefore have negative lag.
Since I cannot see how many date constraints you have or where they are, same for deadlines, I can’t say which ones to fix, but the first thing I would do is remove all of them.
Both the Date Constraints and Deadlines show up in the indicators column or can be seen in the Date Constraints and Deadlines columns. - 0DKDarren Kosa ·Hi Faisal,
Insert the ‘Constraint Type’ and ‘Constraint Date’ columns. Ideally all tasks (apart from the start activity) should have a flexible constraint (As Soon As Possible or As Late As Possible).
The constraints that are probably giving you negative slack are the hard constraints (Must Start On or Must Finish On). Look down the column or use a filter to isolate these tasks and decide whether it needs a new constraint type or you need to change the constraint date.
Regards,
Darren - 0DKDarren Kosa ·Faisal,
Let me make sure I understand you correctly.
1) In the Constraint Date column ALL tasks are ‘NA’
2) In the Constraint Type column ALL tasks are ‘As Soon As Possible’
3) In the Deadline column ALL tasks are ‘NA’
Is this correct?
Also a few more questions…
1) Is your project scheduled from the project finish date? (Project > Project Information)
2) Are there any external links in your project to other projects that have hard constraints?
3) Have you added any VBA code that that uses / changes any of the Start / Finish / Duration / Constraint fields?
Regards,
Darren - 0DKDarren Kosa ·Faisal,
The majority of the time, Total Slack is displayed as whole numbers (days / hours / etc.), but occasionally the Start / Finish dates of tasks don’t exactly match the default Start / End times. This is most likely the cause of your problem.
You need to check to see if this is the case
Go to Tools > Options > Calendar and make a note of the default Start / End times.
Then go Tools > Options > View and change the date format to include hh/mm.
When you look at your schedule in the Gantt View, your Start / Finish dates should look something like this… Tue 08/07/08 08:00.
All you then have to do is scroll through the tasks and look at the hh/mm part of the Start / Finish dates. When you find any times that look something like Tue 08/07/08 08:17, work your way back through the network until you find the offending task and decide what you have to do with it.
Sometimes this is caused by resource work (effort driven) increasing or decreasing the Duration value, other times because split tasks change the Duration and Start / End values by rescheduling uncompleted work to start after the status date.
Regards,
Darren - 0DKDarren Kosa ·Faisal,
OK I’m confused… what is the problem?
Tasks in the Total Slack column have values that = -16d / -20d etc.
Or
Tasks in the Total Slack column have values that = 16.27d / 5.65d etc.
If it is Total Slack = -16d / -20d, have you looked at all the suggestions in post #14? If it is Total Slack = 16.27d / 5.65d, is your schedule effort driven and / or do you have split tasks?
Regards,
Darren - 0TRTrevor Rabey ·This question was answered several times, some time ago.
There are only two possible causes of negative total slack:
1) Date Constraints
2) Deadlines
Can you please confirm that you have shown the columns amended the plan so that you have none of either?
Not thought to be a direct cause compared to above, but worth checking anyway, do you have SS, SF, FF predecessor links and/or negative lag? - 0DKDarren Kosa ·Faisal,
Have all your tasks been progressed to a status date?
Are there any Finish-Start tasks in the schedule where a task successor has a value greater than 0% Complete, but the predecessor is not 100% Complete?
If a successor is 5% Complete for example, it will have an Actual Start. This means that the start of the task has been fixed to that date and will not move (similar to a Must Start On constraint).
If the predecessor task isn’t complete and the Finish date moves past the Actual Start of its successor task, then it will show negative values in the Total Slack column. This may also account for the numbers after the decimal point.
Regards,
Darren
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?