Skip to content

PROGRESS UPDATION PROCESS

Khaja ShariefMember for 18 years 1 month
Created
1
2
0
Hi,
I have a very basic doubt regarding how to register progress in MSP, just about the methodology.

Initial data: project schedule is prepared, base line is saved.
Case-1:
Suppose there is an ’X’ activity in the schedule with a duration of four days (day1,day2,day3,day4).

Consider the frequency of progress entry is daily.

Now the activity has started as per schedule on day1 and I was reported a progress of 10%,
Again on day2, I was reported the progress of 30%
Again on day3, I was reported the progress of 75%
Again on day4, I was reported the progress of 100%

Question:
1.How do you register progress daily in MSP on daily basis ?.
2.How can we get the progress report date wise for the particular activity-X ?.

Can anyone please let me the process. Thanks in advance.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Sharief,
    Presuming the situation at the end of the day is the following: you have worked on specific tasks, you have not worked on other specific tasks
    Open Project, Project Information and make sure the Actual Date is the Windows System date and the Data Date is the day you want to update your project
    Select all the tasks with actual work to be entered for the last day, Tools, Tracking, Update actual work ... at the (data date), for Selected tasks
    Select all the tasks with no actual work for the last day, Tools, Tracking, Schedule the not completed work ... for the Selected tasks
    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?