PROGRESS UPDATION PROCESS
In the Open Standard
Khaja ShariefMember for 18 years 1 month
- Created
- 1
- 2
0
Hi,
I have a very basic doubt regarding how to register progress in MSP, just about the methodology.
Initial data: project schedule is prepared, base line is saved.
Case-1:
Suppose there is an ’X’ activity in the schedule with a duration of four days (day1,day2,day3,day4).
Consider the frequency of progress entry is daily.
Now the activity has started as per schedule on day1 and I was reported a progress of 10%,
Again on day2, I was reported the progress of 30%
Again on day3, I was reported the progress of 75%
Again on day4, I was reported the progress of 100%
Question:
1.How do you register progress daily in MSP on daily basis ?.
2.How can we get the progress report date wise for the particular activity-X ?.
Can anyone please let me the process. Thanks in advance.
I have a very basic doubt regarding how to register progress in MSP, just about the methodology.
Initial data: project schedule is prepared, base line is saved.
Case-1:
Suppose there is an ’X’ activity in the schedule with a duration of four days (day1,day2,day3,day4).
Consider the frequency of progress entry is daily.
Now the activity has started as per schedule on day1 and I was reported a progress of 10%,
Again on day2, I was reported the progress of 30%
Again on day3, I was reported the progress of 75%
Again on day4, I was reported the progress of 100%
Question:
1.How do you register progress daily in MSP on daily basis ?.
2.How can we get the progress report date wise for the particular activity-X ?.
Can anyone please let me the process. Thanks in advance.
1 reply
Oldest firstLog in or join to reply