s-curve in ms project
In the Open Standard
Ammar SamadMember for 19 years 2 months
- Created
- 4
- 3
0
Good day
hi my fellow planners,
One query here, I have put on all input i.e.resources, work & cost in ms project schedule and intend to derived an s-curve based on ’works’. my question is how to produce s-curve for early & late completion. I’ve tryed use "analyze timescaled data in excel" but the result shows early completion data tabulation only. FYI i am using ms project 2003. any one have an idea?
TQ & best regards.
hi my fellow planners,
One query here, I have put on all input i.e.resources, work & cost in ms project schedule and intend to derived an s-curve based on ’works’. my question is how to produce s-curve for early & late completion. I’ve tryed use "analyze timescaled data in excel" but the result shows early completion data tabulation only. FYI i am using ms project 2003. any one have an idea?
TQ & best regards.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?