WBS from project plan

Emmanuel ValentineMember for 18 years 3 months
Created
4
3
0
Hi Everyone

I have just joined a programme that doesn’t have Work Breakdown Structure in place. I am now trying to deduce this from the their master plan (MS Project 2002). How do I go about this.

Thanks
EV

4 replies

Oldest first
  1. 0
    Steve Craine ·
    Hi EV

    Easyest way is insert a colum from the drop down list and find WBS on the list this should give you a good starting
    place

    Steve
  2. 0
    Trevor Rabey ·
    Not sure I understand your question.
    if the plan has headings and sub-headings and you can roll them up and expand various levels etc, then that arrangement of headings, sub-headings and Tasks is the WBS.
    Also, the WBS field shows the same hierachy experessed in numbers, eg 1.1.1 etc.
  3. 0
    Alexandre Faulx-Briole ·
    EV,
    what MS Project names WBS has nothing to do with P3 or PM5/6 WBS, it is rather a hierarchical numbering of the tasks
    basically, you create the MS WBS by indenting subordinate tasks below the summary tasksn not by entering a code like in P3
    MS Project gives a hierarchical number to the tasks, that you can display in Tools, Options, View, Display the ... at the bottom left of the dialog box
    It is also possible to customize the WBS in Project, "Mode Plan" (I am using the french release of MSP, I don’t remember the real name in english), then you will create a WBS coding about the same way that you know in P3; the difference is: the codes will be applied automatically to the tasks, you don not have to do it manually like in P3.
    Good luck,
    Alexandre
  4. 0
    Darren Kosa ·
    Hi Emmanuel

    Not sure if it was a feature in 2k2, but in 2k3 you can export the outline from MS Project into Visio using a WBS Chart Wizard.

    If the current master schedule was constructed using sound planning principles, then the outline should map directly to your WBS. This is because each heading and sub-heading will be associated with a WBS element.

    Differentiating between tasks and WBS elements in MS Project should be a fairly straightforward exercise if the schedule is resource loaded. As a rule of thumb the schedule tasks will have resource assignments against them, the WBS elements won’t.

    If the schedule isn’t resource loaded then hopefully the descriptions in the Name field will help you determine if they are WBS elements or tasks. As an example, ‘Pour Concrete’ lends itself to being a task description whereas ‘Foundations’ could be a WBS element.

    The WBS should also be focused on the scope of project delivery rather than detailing the tasks the have to be completed to produce each deliverable.

    Regards,

    Darren

Log in or join to reply