Consolidated File Views
In the Open Standard
John LMember for 18 years 11 months
- Created
- 1
- 5
0
Dear all,
I have a consolidated file containing around a dozen small projects, none of which are linked.
I want to be able to enter a resource name, and MSP to display IN THEIR ENTIRETY those sub-projects that the resource in question is allocated to. Obviously you can filter the individual tasks that the resource is allocated to, but I need to be able to let a named individual view the whole project that they are involved with, even if they are only linked to one task.
Ant ideas ? Using MSP 2003.
Best regards,
JL