Skip to content

TSPI??

Martin HuntMember for 18 years 1 month
Created
8
4
0
Hi All,

If I was to use the same process used to calculate TCPI but changed the BAC-Actuals for BAC-BCWS then would that give an indication of the schedule performance needed to complete the Project on time??

I’m not sure

Thanks in advance

Martin

8 replies

Oldest first
  1. 0
    Philip Kearney ·
    Hi Martin,

    In theory, it would give that answer.
    But a better option would be the remaining duration/SPI as this would give a more realistic forecast.

    Regards,
    Philip
  2. 0
    Darren Kosa ·
    Hi Martin,

    It’s been a while since I looked at any advanced formula. As I recall you can have TCPI (BAC) and TCPI (EAC).

    I can’t see any reason why you couldn’t therefore use either TSPI (BAC) or TSPI (EAC).

    TSPI could then be calculated by:

    (BAC – BCWP) / (BAC – BCWS)

    Or

    (BAC – BCWP) / (EAC – BCWS)

    You could probably even use IEAC in place of EAC... although you’d have to test it out just to be sure.

    Regards,

    Darren
  3. 0
    Martin Hunt ·
    Thanks for your responses

    Darren I am unsure about the EAC calculation as the BCWS would only calculate as far as the baseline.

  4. 0
    Darren Kosa ·
    Martin,

    Shouldn’t be a problem. In reality the net effect is neutral, it’s just a matter of preference.

    If you think about it EAC is just BAC plus or minus any variance.

    BCWS establishes the baseline, but it’s also the value of all work scheduled to be carried out in a given period of time. This can be cumulative or shown month-by-month.

    Regards,

    Darren
  5. 0
    Darren Kosa ·
    Martin,

    If you think of it another way, EV is all about analysing and forecasting using trends.

    All you really need to decide is do you forecast what you actually think is remaining, or what is remaining in the budget.

    Regards,

    Darren
  6. 0
    Darren Kosa ·
    Martin,

    Chatting with some EV gurus today, I broached the subject of TSPI and was informed unequivocally that it can’t be calculated in the way I suggested. It would always equal 1 which kind of makes sense now I think about it.

    Much better to use the method Phillip suggested in Post #2

    So if you are halfway though a Project / CA / WP and the SPI is 0.90, then the SPI for the remainder of the Project / CA / WP would have to be 1.1.

    Regards,

    Darren
  7. 0
    Philip Kearney ·
    All,

    Sorry for not posting sooner!

    Darren,
    Having gone through your earlier posts, a lot of the suggestions have credibility in theory but from experience, the simplest form is always the best as we are keeping the calculations to a minimum as these things tend to go off on a tangent with a lot of backtracking which can be painstaking work!

    Martin,
    A lot of what Darren has suggested is sufficient if you are a power user as you can get a grasp on what you are looking for...however, I find it for those who are not familiar with the earned value conundrum, sticking to the simplest version until you are confident enough to explain your analysis in layman terms to your superiors as they do not want to get bogged down in the "terminology".

    Lesson learned here...keep it simple!
  8. 0
    Martin Hunt ·
    Hi Philip,

    I personally am very familiar with EV but I understand what you mean about trying to push any excess and complicated metrics reporting onto the program team.

    The point I was trying to get at is before attempting to start using it for the Program I work on if there were any shortfalls.

    Maybe you are right and simplicity is key.

    Thanks for your responses

    Martin

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?