Anybody have detailed installation sequence of A Cinema Theater equiments , i Mean the installation of equipments , audio video caliberation steps etc
please post

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Hemanth,

    Kindly consider the following:

    1) Material submital approval
    2) Shop drawings approval
    3) Procurement
    4) Construction
    a. 1st fix: After block work and before plastering
    b. 2nd fix: before complete plastering
    c. 3rd fix: before complete painting
    5) Commissioning: few days before handing over.
    6) Programming: after moving in

    If you need more specific detail, the best source would be the specialist who is going to install the system for you.

    Best Regards,

    Samer
  2. 0
    Hemanth Kumar ·
    Thank you sameer
    but i was looking for the finer details
    install projector,lay HDMI cable , install speakers etc
  3. 0
    Samer Zawaydeh ·
    Dear Hemanth,

    I have checked with our local Low Current Supplier, and they informed me that it is totally dependent on the system that you are installing.

    So I suggest that you discuss the issue with the supplier and formulate a completion plan as per his sequence of work.

    Best Regards,

    Samer
  4. 0
    Hemanth Kumar ·
    Thank You

    I Discussed With My Supplier and Formulated The Plan
    Thank You For Your Interest & Helpful Mind
  5. 0
    Samer Zawaydeh ·
    Dear Hemanth,

    At your service anytime.

    Best,

    Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?