Milestones ignore calendars in Project 2007
In the Open Standard
Niek ZonneveldMember for 21 years 7 months
- Created
- 3
- 2
0
Just found out another one of the many nasty issues with Project 2007, which I wanted to share with you planners.
In contrast to MSP2003, milestones do ignore task calendars when their duration is 0.
In contrast to proper project scheduling principles, you need to set the milestone duration(!?) to anything >0.005 days to make this work in MSP2007.
Hope this helps.
Niek.
In contrast to MSP2003, milestones do ignore task calendars when their duration is 0.
In contrast to proper project scheduling principles, you need to set the milestone duration(!?) to anything >0.005 days to make this work in MSP2007.
Hope this helps.
Niek.