check if project saved as baseline

Faisal AfsarMember for 18 years 4 months
Created
1
2
0
Dear Friends

i have got a premade plan and now i want to check and confirm whether the project is saved as a base line or not and how many baseline is saved. An early response will be highly appreciated.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Faisal,
    in MS Project, the baseline is a part of the projet
    Go to Tools, Tracking, Save Baseline (Define Baseline in MSP 2007),
    then look at every baseline in the drop down list (from Baseline to Baseline 10): a already saved baseline should be documented with the date it was saved
    BTW, to save a baseline means that the scheduling fields (Duration, Start, Finish, Work, Cost) were pasted in "Baseline xx" fields; it is very different from P3 where the baseline is another project.
    Hope this helps,
    Alexandre