Customise Task Form

Stuart AtkinsonMember for 22 years 9 months
Created
6
2
0
Can someone please tell him how to add the Unique Task ID in the pred. and succ. view in the Task Form.

(MSP 2007)

Thanks,

Stuart

6 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Stuart,
    the only way is to create a new task form; you will use VBA to do that.
    Alexandre
  2. 0
    Colin Blair ·
    Stuart

    A possible way round this is to create a custom table with these fields.

    Split the view and show this table in the bottom.

    Hope this helps

    Colin
  3. 0
    Stuart Atkinson ·
    Thanks Gents.
  4. 0
    Stuart Atkinson ·
    Can either of you guys help me will either method. Unfortunately,my main software is Primavera. I have touched on VBA in the past, but alas!

    I would appreciate further help.

    Stuart
  5. 0
    Alexandre Faulx-Briole ·
    Stuart,
    Open View, Tables [name of the current table], More tables
    Select the table closest to the one you want to use
    Click Copy: the Edit table dialog shows up
    Make any necessary changes in the table: add fields, delete fields, change table name, ...
    Click OK, OK
    Open View, More Views, Create
    Select to create a double pane view: select the Gantt Chart for the upper pane and you new table for the lower one
    Click Apply
    That’s it
    Hope this helps
    Alexandre
  6. 0
    Stuart Atkinson ·
    Cheers Alex,

    I will try it now.

    Stuart

Log in or join to reply