Making MS stable
In the Open Standard
Joel GilbertMember for 23 years 5 months
- Created
- 3
- 2
0
After having worked on Primavera the last few years I found myself on a new Project and they are using MS and I have to deliver the goods.
I have a schedule with resources Manhours and cost and obviously Durations. After baselining I update the schedule and re-schedule but it changes the durations, or if I fix the duration it changes the Manhours and If I fix the Manhours it change the Percentage.
Can anybody tell me what is the correct setting for MS to function stable like Primavera does for instance? Or what the default setting should be as I have inherited this monster and everyone is expecting the usual miracle.
Any urgent Help welcomed
I have a schedule with resources Manhours and cost and obviously Durations. After baselining I update the schedule and re-schedule but it changes the durations, or if I fix the duration it changes the Manhours and If I fix the Manhours it change the Percentage.
Can anybody tell me what is the correct setting for MS to function stable like Primavera does for instance? Or what the default setting should be as I have inherited this monster and everyone is expecting the usual miracle.
Any urgent Help welcomed
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?