Calculated field

Assaf FMember for 18 years 9 months
Created
2
5
0
Hi,
How can I calculate the duration between the task’s finish date and today?
Only including the working days.
I’ve tried [finish]-date() but it uses the entire week and not only working days.

Thanks,
Assaf

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Assaf

    In Lotus 123 there is a formula that counts the number of work days between two calendar dates @networkdays(date 1, date 2,Holiday-range,"weekend")

    You need a range of dates that represent the holidays between date 1 & 2 and the numbers "56" to represent UK Sat & Sun weekends.

    Israel mey have different day numbers.

    There is a similar formula in excell but I don’t think it works so elegantly as Lotus.

    Best Regards

    Mike Testro
  2. 0
    Bo Johnsen ·
    Hi Assaf,

    You just need to change your formula a bit:
    ProjDateDiff(Date(),[Finish],"Standard")/480

    That will do the trick if the working days are to be calculated with respect to your standard calendar (with weekends, holidays, etc. defined) and based on a 8 hour working day. The division by 480 (60min/hr x 8hrs/day)is to get the result from minutes to days. If working e.g. 9 hrs a day the number should be 540 (9x60).

    Regards,

    Bo