constraints

Faisal AfsarMember for 18 years 4 months
Created
5
5
0
Hi All

these is s bit of problem i am trying to create a schedule which is automatically taking up constraints when i am removing these constraints by making it ASAP the dates are coming back to the day when i am creating the schedule ..................any help guys

5 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Faisal

    I hate Microsoft Project and never use it unless I have to.

    You can - I beleive - do a global search and constraint removal.

    There is also a default setting somewhere that sets the attributes for new activities - the standard is to put a constraint on every activity - just plain bonkers.

    You have my deepest sympathy having to use such rubbish.

    Best regards

    Mike Testro.
  2. 0
    Faisal Afsar ·
    rather than your sympathy i would honour your suggestion please
  3. 0
    Mike Testro ·
    Hi Faisal

    Sorry but I have no further suggestions to offer.

    Best regards

    Mike Testro
  4. 0
    Steve Macauley ·
    In MS Project 2003 (it’s probably similar in 2007) there’s an option in Tools->Options->Scheduling called ’New tasks:’, which you can configure to the current date or the project start date. Of course ideally every task in your schedule should be linked to a predecessor.

    When constructing a schedule from scratch is it often useful to create a milestone called ’Project Baseline Start’ with an ’Actual Finish’ set to the current date. This can be linked to any tasks that are due to start immediately.

    Cheerio...
    Steve
  5. 0
    Faisal Afsar ·
    thanks steve

    got the job done