wat is the actual method of finding duration variance (please can)somebody explain in details

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    just display the Variance table in the Task sheet
    Alexandre
  2. 0
    Trevor Rabey ·
    Duration Variance (task field)
    Data Type Duration

    Entry Type Calculated

    Description The Duration Variance field contains the difference between the baseline duration of a task and the total duration (current estimate) of a task.

    How Calculated The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. Microsoft Office Project 2003 then calculates duration variance as follows:

    Duration Variance = Duration - Baseline Duration

    Best Uses Add the Duration Variance field to a task sheet when you want to analyze whether your schedule is taking more or less time than originally planned.

    Example You set a baseline for your project three months ago, and you now want to review duration variances for the tasks. You add the Duration Variance field to the Task Sheet view to analyze the project’s progress and performance to date.

    Remarks If the duration variance is a negative number, the task is scheduled to take less time than originally planned. If the duration variance is a positive number, the task is scheduled to take more time than planned. If the duration variance is zero, the task is taking exactly as much time as originally planned.

    The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. To set a baseline, point to Tracking on the Tools menu, and then click Save Baseline. This copies the current value for the scheduled Duration field into the corresponding Baseline Duration field.

    You can use the Tracking Gantt view to see the duration variance shown graphically with Gantt bars.
  3. 0
    Mukunda Y ·
    faisal
    duration varialnce is the difference between the planned & actual duration...