Planned % Complete - MS Project
In the Open Standard
Kayode OniMember for 19 years 5 months
- Created
- 6
- 5
0
Hi Guys,
A little query using the formula below to calculate planned % complete.
IIf([Baseline1 Start]>[Status Date],0,IIf([Baseline1 Finish]<=[Status Date],1,ProjDateDiff([Status Date],[Baseline1 Start],"Standard")/ProjDateDiff([Baseline1 Finish],[Baseline1 Start],"Standard")))
Using the average option for Roll Up summary tasks, gives the wrong calculation, especially when milestones are involved. (By the way, "Use formula" doesnt give an accurate projection either)
Does anyone know how to do weighted average using this formula?
Many thanks.
A little query using the formula below to calculate planned % complete.
IIf([Baseline1 Start]>[Status Date],0,IIf([Baseline1 Finish]<=[Status Date],1,ProjDateDiff([Status Date],[Baseline1 Start],"Standard")/ProjDateDiff([Baseline1 Finish],[Baseline1 Start],"Standard")))
Using the average option for Roll Up summary tasks, gives the wrong calculation, especially when milestones are involved. (By the way, "Use formula" doesnt give an accurate projection either)
Does anyone know how to do weighted average using this formula?
Many thanks.
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?