Program Comparison
In the Open Standard
Vijayasarthty SMember for 20 years 3 months
- Created
- 2
- 3
0
I have a couple of problems.
1) My Client has asked me to generate a weekly report showing the planned % Complete in MS Project. Can i do it in MSP directly (like in primavera using a target) or must i employ arithmetic formulae inserting a new field.
2) My current finish variance is being displayed as 18.34 days etc, can i eliminate this once for by doing some alterations to ensure that duration must calculated in whole numbers (days) only?.
3) As indicated above, my finish variance is being displayed in decimals. I tried using the following formulae text1 (new field) = ABS ([Finish variance]) and i got wierd values in the columns like -1051 etc, is this because MSP treats Finish Variance as a Date Field?
Regards,
Vijay
1) My Client has asked me to generate a weekly report showing the planned % Complete in MS Project. Can i do it in MSP directly (like in primavera using a target) or must i employ arithmetic formulae inserting a new field.
2) My current finish variance is being displayed as 18.34 days etc, can i eliminate this once for by doing some alterations to ensure that duration must calculated in whole numbers (days) only?.
3) As indicated above, my finish variance is being displayed in decimals. I tried using the following formulae text1 (new field) = ABS ([Finish variance]) and i got wierd values in the columns like -1051 etc, is this because MSP treats Finish Variance as a Date Field?
Regards,
Vijay
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?