Project 2007 to P3

Nithin ThomasMember for 20 years 8 months
Created
2
3
0
Gents,

Any info on the above just cant seem to work around. I am trying to convert projects 2007 to a P3 file.

Regards
Nithin

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Nithin,
    P3 can only read MS Project’s MPX files and MSP 2007 (nor 2003 btw) cannot generate MPX files.
    Download the MppToMpx.exe app from the Primavera Support site, or Mpx2K from www.sciforma.com
    You could also visit Paul E. Harris site http://www.eh.com.au/ and download his whitepaper on the subject
    Alexandre
  2. 0
    Rafael Davila ·
    Or you can download the MppToMpx.exe app from

    http://www.projectstatus.com/pub/