Status date in Microsoft Project
In the Open Standard
Fernando TubiaoMember for 17 years
- Created
- 6
- 5
0
When you press F9 in P3 all the activities that have not been updated are re-schedule after the data date OR if you use the Update option, all the activities within the update period are "actualized". This does not happen in MS Project; you shift the Status Date and "nothing" happens (you can see activities with 0% in the left side - where the actuals are supposed to be; these activities do not move automatically)
Why don’t the activities move or update when you shift the Status Date as it happens when you shift the Data Date in P3 (F9)?
Why don’t the activities move or update when you shift the Status Date as it happens when you shift the Data Date in P3 (F9)?
6 replies
Oldest firstLog in or join to reply