Extended Project
In the Open Standard
Knapp RahsiaMember for 16 years 9 months
- Created
- 1
- 3
0
Hello
My first post here
My project that I’ve been involved with had some delays. So I need to reschedule the Microsoft Project schedule. Problem occur when some of the work only done by 20% or 30% or has a value. The work that had not been done yet is not a problem because I can change the start work date.
Which is the best?
1. I add new task that only contains delay work?. But I believe it will affect almost all the aspect of cost, % progress, ...
2. Using split task?. I split the task into two parts and leave the work done to the left part. Btw, is there any other way to split the task other than clicking the mouse and drag the bar to adjust the day?
3. or you have another option?
thanks.
knapp
My first post here
My project that I’ve been involved with had some delays. So I need to reschedule the Microsoft Project schedule. Problem occur when some of the work only done by 20% or 30% or has a value. The work that had not been done yet is not a problem because I can change the start work date.
Which is the best?
1. I add new task that only contains delay work?. But I believe it will affect almost all the aspect of cost, % progress, ...
2. Using split task?. I split the task into two parts and leave the work done to the left part. Btw, is there any other way to split the task other than clicking the mouse and drag the bar to adjust the day?
3. or you have another option?
thanks.
knapp
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?